Capital Costs

The initial capital requirement for the Project is estimated to be $439.5 M, as detailed in Table 5.

Table 5. Pre-production Capital Costs

----------------------------------------------------------------------------Items                                                          Estimate (M$)----------------------------------------------------------------------------Site Development                                                         7.4Underground Mining                                                      38.5Underground Process Facilities                                          11.7Limestone Quarry                                                         0.2Processing Plant                                                        63.1Tailings & Waste Rock Management                                        15.5On-Site Infrastructure                                                  61.5Mine Access Road (directs)                                              54.2Project Indirects                                                       91.6Engineering & EPCM                                                      31.4Owner's Costs                                                           17.3----------------------------------------------------------------------------Subtotal Pre-Production Capital                                        392.4----------------------------------------------------------------------------Contingency (12.0%)                                                     47.1----------------------------------------------------------------------------Total Pre-Production Capital                                           439.5----------------------------------------------------------------------------


The Project has a total sustaining capital requirement of $64.0 million. Sustaining capital is required for extension of the main ramp to depth, mobile equipment rebuilds and replacements, and capital improvements.

Reclamation/Closure & Salvage Costs

Total reclamation/closure and salvage costs have been estimated as follows:

Table 6. Reclamation/Closure & Salvage Costs

------------------------------------Items                            M$------------------------------------Reclamation/Closure            13.8Salvage Value                  (7.6)------------------------------------


Operating Costs

Total operating costs for the Project have been estimated as follows:

Table 7. Operating Costs

-------------------------------------------------------Items                                           $/tonne-------------------------------------------------------Mining                                            30.06Processing                                        23.02Power                                             22.58G&A                                               22.47Transportation (Conc. and supplies)               27.83-------------------------------------------------------Total                                            125.96-------------------------------------------------------


This cost represents the Life of Mine Cash Cost of the Project, from years 1 - 9 inclusive.

Financial Analysis and Sensitivities

Using the three year trailing average commodity prices, the study yields a pre-tax NPV8% of $192.7 million and an IRR of 16.5% with a payback period of 3.9 years and a post-tax NPV8% of $146.0 million and an IRR of 14.9% with a payback period of 4.4 years.