News Column

Kirkland Lake Gold Inc.: Fiscal 2013 Q2 Operational and Financial Results

Dec 13 2012 12:00AM

Marketwire

LogoTracker

KIRKLAND LAKE, ONTARIO -- (Marketwire) -- 12/13/12 -- Kirkland Lake Gold Inc. (the "Company"), (TSX: KGI)(AIM: KGI) an operating and exploration gold mining company, today announces financial and operational results for the second quarter of its fiscal year 2013 (August, September, and October 2012).

Mr. Harry Dobson, Chairman commented, "The focus of the Company remains the execution of the Mine Expansion Project to a production capacity of 2,200 tons of ore per day. Reaching this milestone will be a key step towards achieving the Company's goal of becoming a sustainable and consistently profitable intermediate gold mining company. The current critical path activity for this Expansion Project is the Service Cage Project. Regrettably, delays in completing this critical path activity have resulted in a delay in the overall Project, and are preventing the Company from meeting its production goals for the current fiscal year. Accordingly, the Company is reducing its guidance for the year ending April 30 to between 90,000 to 110,000 ounces of gold sold. This setback notwithstanding, the Company does remain committed to reaching the above referenced production capacity of 2,200 tons per day as close to the original plan target date of January 2014 as practicable."

Mr. Mark Tessier, Chief Operating Officer, added, "The current critical path item in this expansion project is the Service Cage Project, which will allow hoisting of ore and waste to begin to exceed the current 1,000 ton per day limit. Unfortunately, the completion of this Project continues to be delayed by technical issues with the hoist, primarily software and electronic issues; and also by additional shaft work that had to be moved up in the overall project schedule, and into the scope of the Service Cage Project. The delay in this Project has delayed the ramp up in ore tonnage produced that should have begun in Q2, has delayed the hiring and training of necessary underground workers, and has delayed development work required to access higher grade ore that was required to allow the Company to produce at the planned ore grades this year."

"The Service Cage Project is close to completion, but due to past delays in this Project, the Company is currently allowing in its projections that the Project will not be fully complete before the end of Q3, and that ore tonnage will not begin to ramp up until mid Q4, as a precaution. The Company is also slowing the expected rate of that ore tonnage ramp up to reflect the additional time that will be required to hire and train needed underground workers, and to reflect the time that will be required to complete the development work in the Mine that has been delayed."

KEY HIGHLIGHTS OF THE QUARTER

--  Net loss before income taxes for the quarter ended October 31, 2012 of    $0.8 million ($0.01 per share). This compares to net loss before taxes    of $0.3 million ($0.00 per share) for the previous quarter and a net    income before taxes of $11.8 million ($0.16 per share) for Q2 of fiscal    2012. Ore production for the quarter continued to be skewed towards    lower grade areas, as access to higher grade ore was restricted due to    delays in the Service Cage Project. Costs were also high as the Company    had completed some hiring and training and committed to other work and    activities in Q1 and Q2 in preparation for the planned production    increases.--  Cash flows generated from operating activities were $10.5 million for    the quarter compared to $2.4 million in the previous quarter and $13.4    million in Q2 of fiscal 2012. Year to date cash flows from operating    activities were $12.9 million compared to $19.7 million in the previous    fiscal year.--  Operating costs for the quarter were $360 per ton of ore ($1,253 per    ounce of gold), compared with $316 per ton ($1,276 per ounce) in the    prior quarter, and $277 per ton ($793 per ounce) in Q2 of fiscal 2012.    The Company expects to lower operating costs to less than $250 per ton    upon completion of the Mine Expansion Project.--  In the quarter, 70,800 tons of ore were produced at a head grade of 0.30    ounces of gold per ton (opt) and a gold recovery rate of 95.74% to    produce 20,358 ounces of gold. Year to date, 141,001 tons of ore have    been produced at a head grade of 0.28 opt and a gold recovery rate of    95.52% to produce 37,754 ounces. Ounces sold in the quarter were 22,345    ounces, bringing the year to date total to 42,309 ounces sold. The head    grade of the ore coming from the South Mine Complex (SMC) in the quarter    was 0.34 opt, which was above the 0.27 opt grade realized in the    previous quarter, but well below the normal grade of ore coming from    that area. The head grade of ore coming from the Main Break in the    quarter was 0.25 opt.--  As at December 12, 2012, the Company's cash resources were $101.1    million. Net of the liability to Queenston and restricted cash, the    Company's cash resources were $71.1 million.--  Work remaining on the Service Cage Project as of December 12 included    some ongoing trials and upgrades planned for operation of the hoist in    Cage mode, completion of shaft work between 53 Level and 54 Level, and    completion of 50% to 60% of the required station work. Commissioning    work on the hoist and cage took up most of the month of November due to    some problems with software and electronics for the control systems and    held back the work in other areas. The work platform remains in the    shaft and is being used in combination with the cage as required for the    shaft work. At present the hoist is operating in cage/work platform mode    for shaft work with no issues, and is also being operated in cage only    mode on a spare/trial basis with no issues.--  The Company is planning to replace the ten ton skips in the existing    conveyance arrangement with newly designed 12.5 ton skips after    completion of the Service Cage Project. Slight modifications to the    shaft loading chairs will be required at the same time. This will    increase the capacity of the mine hoisting plant to 2,275 tons per day    of ore and waste. Completion of additional shaft work prior to January    2014 will bring the capacity of the mine hoisting plant to 3,200 tons    per day. The shaft work brought ahead into the Service Cage Project was    originally part of this later stage of the overall Project.--  The testing of the prototype battery scoop underground has been    completed successfully. The scoop is currently commissioned and in    production and performing very well, and this program is currently    meeting all Project schedule requirements at this time.--  The new ball mill is currently on site; work is ongoing to expand the    mill to 2,200 tons per day capacity.--  The Company workforce totalled 957 employees at quarter-end, up from 907    at the beginning of Q1. The Company is not experiencing difficulty    meeting its workforce requirements in terms of numbers at this time.    However, more hiring of inexperienced underground employees than    expected has been required, with a resultant increase in training    activities, and with lower than planned initial productivities. This has    slightly impacted mining costs this fiscal year.--  The Expansion Project budget remains on track at $95.0 million, of which    $72.7 million had been spent by the end of October, 2012. The Processing    Plant Upgrade, the Hoisting Capacity Upgrade Project, and the remaining    underground mobile equipment purchases represent the largest segments of    unspent Project capital. Project spending in some non critical path    Project areas has been delayed as necessary and where practicable to    match progress on the critical path.--  Subsequent to quarter-end on November 7, the Company completed a $68.5    million (net of transaction costs) private placement of convertible    debentures. The funds will be used in part to fund portions of the    Expansion Project that had been expected to be funded from production.

Continued | 1 | 2 | 3 | Next >>

Story Tools